+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

The Employer’s Agent

The Engineer is deemed to act for the Employer and is essentially the Employer’s agent under the FIDIC Red Book 1999. He is not a wholly impartial intermediary, unless such a role is specified in the Particular Conditions, and there is no general obligation under the FIDIC Red Book 1999 for the Engineer to act independently or impartially. However, when he is required to make a determination under Sub-Clause 3.5, he is obliged to make it a fair determination and when he is obliged to issue an Interim Payment Certificate under Sub-Clause 14.6, or a Final Payment Certificate under Sub-Clause 14.13, he must fairly determine the amount due.

By |February 8th, 2017|featured, Knowledge Hub|Comments Off on The Employer’s Agent

FIDIC 1999 Books – Commentary of Clause 11

Clause 11 requires that the Works shall be in the condition required by the Contract at the end of the Defects Notification Period. Where the Contractor carries out work in the Defects Notification Period, it is not entitled to receive payment if the work was a result of a defect in the design for which the Contractor was responsible. Similarly, if the Plant, Materials or workmanship are not in accordance with the Contract or there is a failure by the Contractor to comply with any other obligation then it is required to remedy the problem without payment. The Employer may obtain an extension of the Defects Notification Period if the Works, a Section or a major piece of Plant cannot be used during the Defects Notification Period. The Contractor is required to remedy any defect during the Defect Notification Period and, if it does not, the Employer may claim against the Contractor. Rights are given to the Contractor to undertake this work subject to the Employer’s reasonable security restrictions. Once the Defects Notification Period has expired the Engineer is required within 28 days, subject to receipt of the Contractor’s Documents and the completion of any tests, to issue a Performance Certificate. It is the Performance Certificate that is deemed to constitute acceptance of the Works. Sub-Clause 11.10 provides that after the Performance Certificate has been issued, each Party will remain liable for the fulfilment of any obligation which remains unperformed at the time. The extent and meaning of this clause is open to debate.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary of Clause 11

The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading

In this article Corbett & Co. Director Andrew Tweeddale addresses whether sub-clause 20.5 is a condition precedent to the commencement of an arbitration or whether it is an obligation, the breach of which will not affect the jurisdiction of the arbitral tribunal to resolve the dispute.

By |August 11th, 2016|Arbitration, Knowledge Hub|Comments Off on The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading

Employers Beware

How important is it for an Employer to give a Sub-Clause 2.5 notice of a set-off or cross-claim under the FIDIC Red Book form of contract? Very, according to the Privy Council in NH International (Caribbean) Limited v National Insurance Property Development Company Limited . It found that: o Sub-Clause 2.5 applies to any claims the Employer wishes to make. o The Employer must make such claims promptly and in a particularised form. o Where the Employer fails to raise a claim as required, the back door of set-off or cross-claims is firmly shut. The case also serves as a warning to Employers who take a relaxed view towards their obligation under Sub-Clause 2.4 to provide reasonable evidence of the financial arrangements they have made and are maintaining to pay the Contract Price. It doesn’t matter how wealthy or important the Employer is (it may be a Government, company or individual with very substantial funds) detailed financial information must still be provided.

By |December 16th, 2015|Knowledge Hub|Comments Off on Employers Beware

PERSERO 2 – Singapore Court of Appeal rules DAB decisions are enforceable by way of interim award

On 27 May 2015, the 160-page reserved judgement of the Singapore Court of Appeal (“CA”) was handed down in Persero 2 - PT Perusahaan Gas Negara (Persero) TBK (“PGN”) v CRW Joint Operation (“CRW”)[1]. It will be regarded a triumph for contractors wishing to enforce DAB decisions. The CA ruled that the interim award issued by the arbitral tribunal ordering enforcement of the DAB’s decision should stand. Using the concept of an “inherent premise”, the CA made two important findings: 1) it was not necessary for the Contractor to refer the failure to pay (the secondary dispute) back to the DAB; and 2) it was not necessary for him to refer the merits (the primary dispute) in the same single arbitration as his application to enforce.

By |September 14th, 2015|Dispute Boards, Knowledge Hub|Comments Off on PERSERO 2 – Singapore Court of Appeal rules DAB decisions are enforceable by way of interim award

FIDIC’S procedures for the appointment of a DAB need improvement

If the parties to a FIDIC contract cannot agree on a suitable DAB member and they have selected FIDIC as their appointing entity, they may request FIDIC to appoint that DAB member. FIDIC’s present procedures however seem less than ideal. They increase the prospect of rejection of the candidate nominated by FIDIC in the first instance and so also the need to repeat the exercise. They could also result in an appointment unacceptable to one or both parties. In my view they need to be revised.

By |September 14th, 2015|Dispute Boards, Knowledge Hub|Comments Off on FIDIC’S procedures for the appointment of a DAB need improvement

Release from Performance – FIDIC’s Clause 19.7 and Other Remedies

Is not uncommon to find that an employer attempts to pass almost all risk in a contract to the contractor. However, such an approach may have unforeseen consequences when events later make completion of the works impossible. Here Andrew Tweeddale considers how and when a contractor might be released from further performance.

By |September 4th, 2015|Knowledge Hub|Comments Off on Release from Performance – FIDIC’s Clause 19.7 and Other Remedies

Edward Corbett’s Practical Legal Guide on FIDIC 4th

FIDIC 4th A PRACTICAL LEGAL GUIDE Edward Corbett is the author of the leading practical legal guide to the International Civil Engineering Conditions, as well as a Supplement addressing the 1992 amendments. Both the book and the software are available from FIDIC's bookshop.

By |January 1st, 2000|Knowledge Hub|Comments Off on Edward Corbett’s Practical Legal Guide on FIDIC 4th
Go to Top