+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC contracts—introduction to the FIDIC Green Book 2021

This Practice Note is an introduction to the FIDIC Green Book 2021 (the Short Form of Contract). It is not a fully detailed clause-by-clause commentary. This article was first published by LexisPSL

By |January 10th, 2023|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC contracts—introduction to the FIDIC Green Book 2021

FIDIC 1999 Books – Commentary on Clause 8

Clause 8 contains all the fundamental provisions relating to the start of the Works, the Time for Completion, delays and the entitlement of the Contractor to an extension of time and of the Employer to delay damages, and finally the circumstances in which a suspension of the Works can occur and the implications for the Parties. 

By |November 14th, 2018|Delay, English Law, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 8

Cherry Picking FIDIC 2017

Much has been said about the new Red, Yellow and Silver Books 2nd Editions launched by FIDIC in December last year. The most obvious comment has been about their size, almost 50,000 words, which is some 60% longer than the 1999 forms. Although the 1999 forms were not perfect, most regular users seem to be agreed that they did not need 20,000 words to fix the issues. This consensus led this author to attempt to cherry-pick the good bits from the 2017 forms and to propose amendments to add the good ideas to the 1999 forms. The amendments apply to all three forms unless it is indicated otherwise.

By |October 29th, 2018|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Dispute Boards, Drafting, featured, Knowledge Hub|Comments Off on Cherry Picking FIDIC 2017

FIDIC 1999 Books – Commentary on Clause 3

Clause 3 deals with the duties and obligations of the Engineer and his assistants.  Sub-Clause 3.1 deals with the role and duties of the Engineer.  The Engineer is deemed to act for the Employer.  The Engineer has no authority to relieve the Contractor of his duties, obligations or responsibilities under the Contract; nor can the Engineer amend the Contract. Under Sub-Clause 3.2 the Engineer can delegate authority to any assistants; however, the Engineer cannot delegate the responsibility to make Determinations.  Under Sub-Clause 3.3 the Engineer may issue instructions or modified Drawings at any time, which are necessary for the execution of the Works.  If the instruction constitutes a Variation, then it is dealt with under Clause 13 [Variations and Adjustments].  The Contractor is required to comply with any instruction given by the Engineer or delegated assistant.  Sub-Clause 3.4 deals with the replacement of the Engineer.  The Employer must not replace the Engineer with someone against whom the Contractor raises reasonable objection. Sub-Clause 3.5 deals with Determinations.  When making a Determination the Engineer should consult with each of the Parties and, if agreement cannot be reached, make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances.  Both Parties are required to give effect to any Determination unless, or until, it is revised under Sub-Clause 20.1 [Claims, Disputes and Arbitration].

By |September 26th, 2018|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 3

FIDIC 1999 Upgrade Launched

Corbett & Co. has published its selection of the best bits of the FIDIC 2017 2nd Editions adapted for use with the 1999 forms. With many people put off by the 50,000+ words of the new editions, the FIDIC 1999 Upgrade will permit users to benefit from FIDIC’s new ideas and improvements.

By |July 17th, 2018|featured, Knowledge Hub|Comments Off on FIDIC 1999 Upgrade Launched

FIDIC 2017 Books – Clause 3 – The Engineer

The main changes: Employer’s consent and neutrality The main changes in Clause 3 are the express provisions in Sub-Clause 3.2 [Engineer’s Duties and Authority] that the Engineer is not required to obtain the Employer’s consent before the Engineer exercises its authority under Sub-Clause 3.7 [Agreement or Determination], and that the Engineer must act “neutrally” when exercising its duties under Sub-Clause 3.7 [Agreement or Determination].  Dictionary definitions suggest that “neutrally” is similar in meaning to the words “independently” or “impartially” found in the FIDIC Red Book 4th edition and the FIDIC Yellow Book 3rd edition. However, the drafting committee believe that by using a different word it will avoid the difficulties raised in the interpretation of independently or impartially in the earlier editions.  This remains to be seen.  The intention is that “the Engineer treats both Parties even-handedly, in a fair minded and unbiased manner”.

By |January 27th, 2018|Knowledge Hub|Comments Off on FIDIC 2017 Books – Clause 3 – The Engineer

FIDIC 1999 Books – Commentary on Clause 13

Sub-Clause 13.1 deals with the right of the Engineer to vary the Contract. This right can be exercised at any time up to the issue of the Taking-Over Certificate. Sub-Clause 13.2 deals with value engineering and permits the Contractor to propose a change which will benefit the Employer. The proposal is prepared at the cost of the Contractor, who designs the change. Sub-Clause 13.3 deals with the procedure prior to the Engineer instructing a variation. The Engineer may request a proposal from the Contractor. However, while the Contractor is preparing the proposal it must proceed with the works. Sub-Clause 13.4 deals with payment in applicable currencies. Sub-Clause 13.5 deals with Provisional Sums and ought to be read with Sub-Clause 1.1.4.10 which defines Provisional Sum as follows:- “a sum (if any) which is specified in the Contract as a provisional sum, for the execution of any part of the Works or for the supply of Plant, Materials or services under Sub-Clause 13.5 [Provisional Sums].” The Provisional Sum can only be used where there is an Engineer’s instruction and the Contractor receives payment for only the work done to which the Provisional Sum relates. Sub-Clause 13.6 deals with daywork. This is where work of a minor or incidental nature is to be carried out. The work is then valued in accordance with the Daywork Schedule in the Contract or if there is no Daywork Schedule then the alternative method of payment as prescribed in the Contract. Sub-Clause 13.7 deals with the Cost arising from changes in the Laws of the Country which affect the Contractor in performance of his obligations under the Contract. Where the Contractor suffers delay or additional Cost then it must give notice under Sub-Clause 20.1 of the Contract. Sub-Clause 13.8 deals with adjustments for changes in cost. This Sub-Clause only applies where the “table of adjustment data” included in the Appendix to Tender has been completed. If the Sub-Clause does apply then the amounts payable to the Contractor for rises and fall in the cost of the Works are adjusted by a formula.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 13
Go to Top