+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC ‘launched’ the FIDIC 2022 reprints at the FIDIC International Construction Users’ Conference 2022, in London. The reception to the changes was mixed – some embraced the clarity; others questioned the significance and cost. This article draws your attention to 10 of the key areas of change in respect of the FIDIC Red Book 2017 including the definition of Claim, matters to be agreed or determined, the definition of Dispute and Exceptional Events.

By |January 18th, 2023|Adjudication / Dispute Boards / ADR, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC 1999 Books – Commentary on Clause 8

Clause 8 contains all the fundamental provisions relating to the start of the Works, the Time for Completion, delays and the entitlement of the Contractor to an extension of time and of the Employer to delay damages, and finally the circumstances in which a suspension of the Works can occur and the implications for the Parties. 

By |November 14th, 2018|Delay, English Law, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 8

Variation Provisions in the FIDIC Yellow Book 2017

Much has already been written concerning the new FIDIC forms of contract published in December 2017. They are approximately 50 % longer and sought to set out the various procedure in much greater detail with the object of both encouraging good practice and reducing the scope for disputes. Numerous minor amendments have also been made. The purpose of this article is to look in more detail at the provisions dealing with Variations, these being amongst the most frequently scrutinised in practice.

By |October 29th, 2018|featured, Knowledge Hub|Comments Off on Variation Provisions in the FIDIC Yellow Book 2017

FIDIC 1999 Books – Commentary on Clause 14

Clause 14 deals with all aspects of payment.  It also deals with the Statement at Completion, the Final Payment Certificate, Discharge and Cessation of the Employer’s Liability. The Clause provides that this is a re-measurement contract and that the quantities stated in the Bill of Quantities are estimated.  There is provision for an advance payment to be made to the Contract.  Applications for Interim Payment Certificates are made monthly and these must be supported by documents and a report on progress.   Unless the amount assessed is less than the minimum amount set out in the Appendix to Tender, the Engineer has 28 days to issue an Interim Payment Certificate, which states the amount the Engineer fairly determines to be due.  The Employer thereafter has an obligation to pay the amount certified, in the currencies named in the Appendix to Tender.  In the event that payment is not received the Contractor can claim financing charges compounded monthly. Fifty per cent of the retention monies are paid when the Taking-Over Certificate is issued.  Where there are Sections then a proportion is paid.  The balance of retention is paid on the expiry of the latest Defects Notification Period or, where there are Sections, a proportion at the expiry of the Defects Notification Period for that Section.    Within 84 days of receiving the Taking-Over Certificate the Contractor submits a Statement at Completion.  This must include an estimate of all sums which the Contractor considers due. Within 56 days of receiving a Performance Certificate, the Contractor submits a Final Statement.  The Contractor must also submit with the Final Statement a written discharge which confirms that the total of the Final Statement represents full and final settlement of all moneys due.  The Engineer then issues to the Employer a Final Payment Certificate.  The Contract states that the Employer shall have no liability to the Contractor except to the extent that the Contractor has included an amount expressly for that matter in the Final Statement and also the Statement at Completion.

By |September 26th, 2018|featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 14

FIDIC 1999 Books – Commentary on Clause 3

Clause 3 deals with the duties and obligations of the Engineer and his assistants.  Sub-Clause 3.1 deals with the role and duties of the Engineer.  The Engineer is deemed to act for the Employer.  The Engineer has no authority to relieve the Contractor of his duties, obligations or responsibilities under the Contract; nor can the Engineer amend the Contract. Under Sub-Clause 3.2 the Engineer can delegate authority to any assistants; however, the Engineer cannot delegate the responsibility to make Determinations.  Under Sub-Clause 3.3 the Engineer may issue instructions or modified Drawings at any time, which are necessary for the execution of the Works.  If the instruction constitutes a Variation, then it is dealt with under Clause 13 [Variations and Adjustments].  The Contractor is required to comply with any instruction given by the Engineer or delegated assistant.  Sub-Clause 3.4 deals with the replacement of the Engineer.  The Employer must not replace the Engineer with someone against whom the Contractor raises reasonable objection. Sub-Clause 3.5 deals with Determinations.  When making a Determination the Engineer should consult with each of the Parties and, if agreement cannot be reached, make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances.  Both Parties are required to give effect to any Determination unless, or until, it is revised under Sub-Clause 20.1 [Claims, Disputes and Arbitration].

By |September 26th, 2018|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 3

FIDIC 1999 Books – Commentary on Clause 19

Clause 19 deals with two distinct events: (1) Force Majeure; and (2) release from performance under the law. Force Majeure is often narrowly defined under the laws of many countries; however, within the FIDIC 1999 forms of contract it has a much broader meaning. The terminology used by FIDIC has therefore sometimes been criticized as being misleading.

By |September 28th, 2017|featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 19

FIDIC 1999 Books – Commentary on Clause 13

Sub-Clause 13.1 deals with the right of the Engineer to vary the Contract. This right can be exercised at any time up to the issue of the Taking-Over Certificate. Sub-Clause 13.2 deals with value engineering and permits the Contractor to propose a change which will benefit the Employer. The proposal is prepared at the cost of the Contractor, who designs the change. Sub-Clause 13.3 deals with the procedure prior to the Engineer instructing a variation. The Engineer may request a proposal from the Contractor. However, while the Contractor is preparing the proposal it must proceed with the works. Sub-Clause 13.4 deals with payment in applicable currencies. Sub-Clause 13.5 deals with Provisional Sums and ought to be read with Sub-Clause 1.1.4.10 which defines Provisional Sum as follows:- “a sum (if any) which is specified in the Contract as a provisional sum, for the execution of any part of the Works or for the supply of Plant, Materials or services under Sub-Clause 13.5 [Provisional Sums].” The Provisional Sum can only be used where there is an Engineer’s instruction and the Contractor receives payment for only the work done to which the Provisional Sum relates. Sub-Clause 13.6 deals with daywork. This is where work of a minor or incidental nature is to be carried out. The work is then valued in accordance with the Daywork Schedule in the Contract or if there is no Daywork Schedule then the alternative method of payment as prescribed in the Contract. Sub-Clause 13.7 deals with the Cost arising from changes in the Laws of the Country which affect the Contractor in performance of his obligations under the Contract. Where the Contractor suffers delay or additional Cost then it must give notice under Sub-Clause 20.1 of the Contract. Sub-Clause 13.8 deals with adjustments for changes in cost. This Sub-Clause only applies where the “table of adjustment data” included in the Appendix to Tender has been completed. If the Sub-Clause does apply then the amounts payable to the Contractor for rises and fall in the cost of the Works are adjusted by a formula.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 13

FIDIC 1999 Books – Commentary on Clause 5

Clause 5 defines a ‘nominated Subcontractor’ as either a Subcontractor who is stated in the Contract as being ‘nominated’; or who the Engineer instructs the Contractor to employ as a Subcontractor under clause 13. The Contractor may object to employing a nominated Subcontractor. A number of grounds are deemed to be reasonable for objecting and these include: where there are reasons to believe that the Subcontractor does not have sufficient resources, competence or financial strength to complete the subcontracted works; where the Subcontractor refuses to agree to indemnify the Contractor for any negligence; or where the Subcontractor does not agree to carry out the works so as not to put the Contractor in breach of its own obligations. If the Employer requires that the Contractor employ a nominated Subcontractor where a reasonable objection has been made then it must agree to indemnify the Contractor. The Contractor is required to pay to the nominated Subcontractor the amounts which the Engineer certifies to be due in accordance with the Subcontract. This sum is then added to the Contract Price as well as any amount for overheads and profit as stated in the appropriate schedule or Appendix to Tender. However, before issuing a Payment Certificate to the Contractor the Engineer may ask for evidence that previous payments have been made to the nominated Subcontractor. If evidence is not provided by the Contractor or the Contractor does not satisfy the Engineer that there are grounds for withholding payment then the Employer may at his discretion pay the nominated Subcontractor directly.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 5
Go to Top