+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 1999 Books – Commentary on Clause 16

Clause 16 deals with suspension and termination by the Contractor. Sub-Clause 16.1 deals with the Contractor’s right to suspend work in the event that the Engineer fails to certify in accordance with Sub-Clause 14.6 [Payment Certificates] or the Employer fails to comply with Sub-Clause 2.4 [Employer’s Financial Arrangements] or Sub-Clause 14.7 [Payment]. Prior to the Contractor suspending work it must give 21 days’ notice. The right to suspend does not affect the Contractor’s entitlement to terminate or claim financing charges. In the event that the Contractor suffers delay or cost as a result of suspension it must give notice under Sub-Clause 20.1 [Contractor’s Claims]. Sub-Clause 16.2 deals with the Termination by the Contractor. There are seven grounds specified. In most cases the Contractor may give 14 days’ notice if it intends to terminate the contract; however, where there has been a prolonged suspension under Sub-Clause 8.11 [Prolonged Suspension] or, inter alia, bankruptcy, liquidation, insolvency or receiving or administration orders have been made against the Employer then the Contractor may by notice terminate immediately. Sub-Clause 16.3 deals with Cessation of Work by the Contractor and Removal of the Contractor’s Equipment. This Sub-Clause applies where the termination takes place under Sub-Clause 15.5 [Employer’s Entitlement to Termination]; Sub-Clause 16.2 [Termination by Contractor]; or Sub-Clause 19.6 [Optional Termination, Payment and Release]. Sub-Clause 16.4 deals with Payment on Termination. Once termination under Sub-Clause 16.2 [Termination by Contractor] has taken effect then the Contractor is entitled to the return of the Performance Security; payment in accordance with Sub-Clause 19.6 [Optional Termination, Payment and Release] and loss of profit or other loss and damage sustained by the contractor as a result of termination.

By |February 21st, 2017|featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 16

The Risk of Relying on the Obrascon case’s ruling on Sub-Clause 20.1 Claim Notices

Contractors are sometimes concerned about the politics of their FIDIC 1999 Sub-Clause 20.1 notices. Some Contractors may consider that serving Sub-Clause 20.1 notices may send the wrong message, particularly in the honeymoon period when the works have just begun. However, the consequences of failing to serve a timely claim notice are so dire that doubtless the issue is regularly on every Contractor’s mind. The case of Obrascon Huarte Lain SA v Her Majesty's Attorney General for Gibraltar1 in the Technology and Construction Court of England and Wales provided some welcomed relief to many Contractors worldwide who may now attempt to rely on its finding on the timing of claim notices when postponing service of these crucial notices.

By |February 8th, 2017|featured, Knowledge Hub|Comments Off on The Risk of Relying on the Obrascon case’s ruling on Sub-Clause 20.1 Claim Notices

FIDIC 1999 Books – Commentary on Clause 4

Clause 4 sets out various obligations which fall on the Contractor under the Contract and which cannot easily be classified elsewhere. The obligations under Clause 4 are of a wide range covering 24 different topics. Sub-Clause 4.1 sets out the Contractor’s general obligation to carry out his duties in accordance with the contract. Clause 4 of the FIDIC Red Book 1999 amalgamates various Contractor obligations under one provision. However this Clause 4 is not exclusive as there are also other Contractor obligations scattered throughout the Contract. Other significant general obligations which could equally have been included in Clause 4 (and which should be read in conjunction with this Clause 4) are as follows: • Sub-Clause 1.3 [Communications] • Sub-Clause 1.7 [Assignment] • Sub-Clause 1.8 [Care and Supply of Documents] • Sub-Clause 1.9 [Delayed Drawings or Instructions] • Sub-Clause 1.10 [Employer’s Use of Contractor’s Documents] • Sub-Clause 1.12 [Confidential Details] • Sub-Clause 1.13 [Compliance with Laws] • Clause 6 [Staff and Labour] • Clause 7 [Plant, Materials and Workmanship] • Sub-Clause 8.2 [Time for Completion] • Sub-Clause 8.3 [Programme]

By |November 23rd, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 4

Murphy’s Law

Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.

By |October 3rd, 2016|Bonds, Delay, English Law, Knowledge Hub|Comments Off on Murphy’s Law

FIDIC 1999 Books – Commentary on Clause 13

Sub-Clause 13.1 deals with the right of the Engineer to vary the Contract. This right can be exercised at any time up to the issue of the Taking-Over Certificate. Sub-Clause 13.2 deals with value engineering and permits the Contractor to propose a change which will benefit the Employer. The proposal is prepared at the cost of the Contractor, who designs the change. Sub-Clause 13.3 deals with the procedure prior to the Engineer instructing a variation. The Engineer may request a proposal from the Contractor. However, while the Contractor is preparing the proposal it must proceed with the works. Sub-Clause 13.4 deals with payment in applicable currencies. Sub-Clause 13.5 deals with Provisional Sums and ought to be read with Sub-Clause 1.1.4.10 which defines Provisional Sum as follows:- “a sum (if any) which is specified in the Contract as a provisional sum, for the execution of any part of the Works or for the supply of Plant, Materials or services under Sub-Clause 13.5 [Provisional Sums].” The Provisional Sum can only be used where there is an Engineer’s instruction and the Contractor receives payment for only the work done to which the Provisional Sum relates. Sub-Clause 13.6 deals with daywork. This is where work of a minor or incidental nature is to be carried out. The work is then valued in accordance with the Daywork Schedule in the Contract or if there is no Daywork Schedule then the alternative method of payment as prescribed in the Contract. Sub-Clause 13.7 deals with the Cost arising from changes in the Laws of the Country which affect the Contractor in performance of his obligations under the Contract. Where the Contractor suffers delay or additional Cost then it must give notice under Sub-Clause 20.1 of the Contract. Sub-Clause 13.8 deals with adjustments for changes in cost. This Sub-Clause only applies where the “table of adjustment data” included in the Appendix to Tender has been completed. If the Sub-Clause does apply then the amounts payable to the Contractor for rises and fall in the cost of the Works are adjusted by a formula.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 13

FIDIC 1999 Books – Commentary on Clause 12

FIDIC 1999 is a re-measurement contract so that the Employer takes the risk of variations to the quantities and, in certain cases, to the rates and prices which may be applied for the work executed. If the Employer wishes to employ a Contractor on a lump-sum or cost plus basis then this clause needs to be deleted. Sub-Clause 12.1 deals with the measurement of the works. Sub-Clause 12.2 does not include a reference to any standard method of measurement but states that the works are to be measured in accordance with the Bill of Quantities or other applicable Schedules. The lack of reference to a particular standard method of measurement has been criticised. Sub-Clause 12.3 deals with evaluating the appropriate rate or price for the works. There are three methods of evaluating the works:- a) The rate or price specified for such item in the Contract; but if there is no such item b) The rate or price specified for similar work. c) However, in certain specified circumstances, a new rate or price shall be appropriate. Sub-Clause 12.4 deals with the valuation of omissions from the Work. As this is a re-measurement contract there is no warranty that the quantities measured in the Bill of Quantities are accurate. Nael Bunni suggests that when quantities within the Bill of Quantities are exceeded then payment should be at the rates set out in the Bill. There have been some cases where the courts have adopted differing approaches; however, in those cases the wording of the remeasurement clause differed to that within FIDIC. These decisions have been described by Dr. Bunni as being controversial.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 12

FIDIC 1999 Books – Commentary of Clause 11

Clause 11 requires that the Works shall be in the condition required by the Contract at the end of the Defects Notification Period. Where the Contractor carries out work in the Defects Notification Period, it is not entitled to receive payment if the work was a result of a defect in the design for which the Contractor was responsible. Similarly, if the Plant, Materials or workmanship are not in accordance with the Contract or there is a failure by the Contractor to comply with any other obligation then it is required to remedy the problem without payment. The Employer may obtain an extension of the Defects Notification Period if the Works, a Section or a major piece of Plant cannot be used during the Defects Notification Period. The Contractor is required to remedy any defect during the Defect Notification Period and, if it does not, the Employer may claim against the Contractor. Rights are given to the Contractor to undertake this work subject to the Employer’s reasonable security restrictions. Once the Defects Notification Period has expired the Engineer is required within 28 days, subject to receipt of the Contractor’s Documents and the completion of any tests, to issue a Performance Certificate. It is the Performance Certificate that is deemed to constitute acceptance of the Works. Sub-Clause 11.10 provides that after the Performance Certificate has been issued, each Party will remain liable for the fulfilment of any obligation which remains unperformed at the time. The extent and meaning of this clause is open to debate.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary of Clause 11

The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading

In this article Corbett & Co. Director Andrew Tweeddale addresses whether sub-clause 20.5 is a condition precedent to the commencement of an arbitration or whether it is an obligation, the breach of which will not affect the jurisdiction of the arbitral tribunal to resolve the dispute.

By |August 11th, 2016|Arbitration, Knowledge Hub|Comments Off on The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading

FIDIC 1999 Books – Commentary on Clause 10

Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens when the Works (a) pass the Tests on Completion; (b) are substantially complete; (c) any contractual requirements relating to Taking-Over have been met; and (d) the Taking-Over Certificate has been issued or is deemed to have been issued. Sub-Clauses 10.2 and 10.3 deal with deemed Taking-Over where the Employer uses part of the Works or interferes with the Tests on Completion for more than 14 days. The failure to issue a Taking-Over Certificate by the Engineer, where the Employer has taken into commercial use the Works, will amount to a breach of contract.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 10

FIDIC 1999 Books – Commentary on Clause 9

Clause 9 deals with the Tests on Completion. Sub-Clause 9.1 requires the Contractor to give notice when it is ready to carry out the Tests on Completion. Tests on Completion are a defined term at Sub-Clause 1.1.3.4. Sub-Clause 9.2 deals with delayed testing caused by either the Employer or the Contractor. Sub-Clause 9.3 deals with retesting after a failure to pass the Tests on Completion. Sub-Clause 9.4 deals with a failure to meet the requirements of the contract after retesting.

By |August 1st, 2016|Delay, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 9

FIDIC 1999 Books – Commentary on Clause 5

Clause 5 defines a ‘nominated Subcontractor’ as either a Subcontractor who is stated in the Contract as being ‘nominated’; or who the Engineer instructs the Contractor to employ as a Subcontractor under clause 13. The Contractor may object to employing a nominated Subcontractor. A number of grounds are deemed to be reasonable for objecting and these include: where there are reasons to believe that the Subcontractor does not have sufficient resources, competence or financial strength to complete the subcontracted works; where the Subcontractor refuses to agree to indemnify the Contractor for any negligence; or where the Subcontractor does not agree to carry out the works so as not to put the Contractor in breach of its own obligations. If the Employer requires that the Contractor employ a nominated Subcontractor where a reasonable objection has been made then it must agree to indemnify the Contractor. The Contractor is required to pay to the nominated Subcontractor the amounts which the Engineer certifies to be due in accordance with the Subcontract. This sum is then added to the Contract Price as well as any amount for overheads and profit as stated in the appropriate schedule or Appendix to Tender. However, before issuing a Payment Certificate to the Contractor the Engineer may ask for evidence that previous payments have been made to the nominated Subcontractor. If evidence is not provided by the Contractor or the Contractor does not satisfy the Engineer that there are grounds for withholding payment then the Employer may at his discretion pay the nominated Subcontractor directly.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 5

FIDIC 1999 Books – Commentary on Clause 2

Corbett & Co. has devised a helpful commentary on FIDIC 1999 books Clause 2. Clause 2 sets out certain obligations which are imposed on the Employer; however, this is by no means all the Employer’s obligations. The obligation to pay the Contractor, for example, is found in Sub-Clause 14.7 and the obligation to Take-Over the Works is found at Sub-Clause 10.1. The first obligation imposed on the Employer under this Clause is to give to the Contractor a right of access. Sub-Clause 2.1 needs to be read alongside Sub-Clauses 2.3 and 4.6, which make it clear that possession of the Site need not be exclusive. Sub-Clause 2.2 imposes on the Employer an obligation to assist the Contractor when requested to obtain permits, licences or approvals required by the laws of the Country. The obligation to reasonably assist is not an absolute obligation and generally will not mean the Employer will have to expend money on fulfilling the obligation. Sub-Clause 2.3 imposes on the Employer an obligation similar to that imposed on the Contractor under Sub-Clause 4.6. The Employer is responsible for any failure by its personnel to co-operate with the Contractor or to comply with safety regulations, take care of persons on Site, make sure the Site is reasonably free from unnecessary obstructions, and protect the environment. Sub-Clause 2.4 imposes on the Employer an obligation to show that financial arrangements have been made and are in place to enable it to pay the Contract Price. Sub-Clause 2.5 deals with the Employer’s Claims and requires that the Employer give notice and particulars of its claim before the Engineer makes a Determination under Sub-Clause 3.5. The Employer cannot set-off any claims it may have against the Contractor unless it complies with this Sub-Clause.

By |July 27th, 2016|Dispute Boards, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 2

FIDIC 1999 Books – Commentary on Clause 1

Clause 1 sets out many of the boilerplate clauses within the Contract and provides a number of definitions which are used thereafter. The Clause has been substantially changed from the Red Book 4th edn with a raft of new clauses added. Sub-Clause 1.3 deals with communications and states that approvals, certificates, consents and determinations shall not be unreasonable withheld or delayed. The assignment provisions in Sub-Clause 1.7 have now changed so that restriction on assignment applies to both the Contractor and Employer. Delayed Drawings and Instructions is dealt with at Sub-Clause 1.9. This was previously dealt with at Clause 6.4 of the Red Book 4th edn and it is unclear why such an important provision has now been rolled up in the General Provisions clause.

By |July 19th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 1

Frozen Out

What relief does FIDIC provide when bank accounts are frozen as a result of war, hostilities, rebellion, terrorism etc.? Maybe not as much as you think. Tensions in Africa and the Middle East have seen the implementation of numerous international financial sanctions. While these sanction regimes vary in execution and enforcement they often freeze assets and prevent financial transactions. These restrictions may impact on the Employer’s performance of its payment obligations under the Contract. This can have serious consequences where the Contractor is entitled to suspend or terminate on notice for non-payment. Many parties automatically assume that financial sanctions will be recognised as force majeure. However, this may not be the case.

By |December 16th, 2015|Knowledge Hub|Comments Off on Frozen Out

Where Do FIDIC Cases Go?

FIDIC is arguably the most widely used standard form of international construction contract but reported FIDIC cases are rare. Is it time for an increased publication of FIDIC cases? There are three categories of decisions arising out of FIDIC dispute resolution provisions: 1. Decisions of the Engineer or the Dispute Adjudication Board (DAB), which will generally not be published or reported to anyone other than the parties involved in the dispute. 2. Decisions of arbitral tribunals, which are not usually made public although this is subject to certain exceptions. 3. Decisions of national courts, which are a relatively rare occurrence for the reasons discussed below.

By |December 16th, 2015|Arbitration, Dispute Boards, Knowledge Hub|Comments Off on Where Do FIDIC Cases Go?

Employers Beware

How important is it for an Employer to give a Sub-Clause 2.5 notice of a set-off or cross-claim under the FIDIC Red Book form of contract? Very, according to the Privy Council in NH International (Caribbean) Limited v National Insurance Property Development Company Limited . It found that: o Sub-Clause 2.5 applies to any claims the Employer wishes to make. o The Employer must make such claims promptly and in a particularised form. o Where the Employer fails to raise a claim as required, the back door of set-off or cross-claims is firmly shut. The case also serves as a warning to Employers who take a relaxed view towards their obligation under Sub-Clause 2.4 to provide reasonable evidence of the financial arrangements they have made and are maintaining to pay the Contract Price. It doesn’t matter how wealthy or important the Employer is (it may be a Government, company or individual with very substantial funds) detailed financial information must still be provided.

By |December 16th, 2015|Knowledge Hub|Comments Off on Employers Beware

FIDIC’s Sub-Clause 20.5 – A Condition Precedent to Arbitration

The 1999 FIDIC forms of contract contain a number of obligations and/or conditions precedent that require (a) a party to give notice of a claim (Sub-Clauses 20.1 and 2.5); (b) refer the claim to the Engineer (Sub-Clauses 20.1 and 3.5); and (c) submit the dispute to a Dispute Adjudication Board (“DAB”) (Sub-Clause 20.4). If either party gives a notice of dissatisfaction relating to the DAB’s Decision then Sub-Clause 20.5 provides that: “Where notice of dissatisfaction has been given under Sub-Clause 20.4 above, both Parties shall attempt to settle the dispute amicably before the commencement of arbitration. However, unless both Parties agree otherwise, arbitration may be commenced on or after the fifty-sixth day after the day on which notice of dissatisfaction was given, even if no attempt at amicable settlement has been made.”

By |December 16th, 2015|Adjudication / Dispute Boards / ADR, Arbitration, Knowledge Hub|Comments Off on FIDIC’s Sub-Clause 20.5 – A Condition Precedent to Arbitration
Go to Top